Problems inherent in multi-party construction disputes: Consolidation of Arbitration
Share
Author: Thuo
The construction industry in Kenya is witnessing continuous growth, with both government and
private
sectors investing billions in construction projects across the country. Major projects include
the construction
of ports, railways, major roads, shopping malls, skyscrapers, etc.
With the rise of construction activities in the country, construction disputes are also
increasing. In 2018
alone, for example, Courts of Appeal rendered more than five judgments in respect of
construction
contracts, not to mention numerous judicial decisions that were rendered by the High Court,
subordinate
courts, arbitrators, and mediators.
The most common causes of construction disputes in Kenya are failure to comply with contractual
obligations and contract omissions or errors. Another cause of the dispute is the failure to
properly administer
the contract.
Many parties to a construction contract choose to resolve disputes through arbitration because
contracting parties usually agree on the arbitrator, save time, and promote confidentiality.
Over the years, I have noted that many parties to construction contracts downplay the importance
of
including a provision that deals specifically with consolidation of arbitration when drafting
construction
contracts. This is despite knowing that construction disputes can extend their effect to parties
not
contemplated in the contract.
It is common to see either an owner or a contractor having at least two or more unique, non-
interlocking contracts with arbitration provisions. When a dispute arises, those inconsistent
arbitration
clauses not only delay the resolution of the substantive dispute but can also lead to
inconsistent decisions.
For a moment, imagine a scenario where a dispute involves an owner, contractor, and architect.
If
the conflict between the owner and the contractor and one between the owner and the architect
are
resolved in different arbitral forums, the architect may successfully blame the contractor for
poor
workmanship and the contractor may successfully blame the architect for delays in giving
required
information or design defects. Consequently, both forums may dismiss the owner’s claim for
damages
despite the owner being the only blameless party in the process.
A unified arbitral proceeding is therefore necessary for most construction disputes if the
interests of all
parties are to be protected. It is the only way the pillars of arbitration such as efficiency
and consistency can
be safeguarded from such disputes.
In Kenya, there is only one arbitral institution that has adopted provisions in its
institutional rules that
allow the consolidation of related disputes. The Nairobi Centre One International Arbitration
(Arbitration) Rules, 2015 contain a set of provisions for consolidation.
The only issue I have with the Nairobi Centre International Arbitration (Arbitration) Rules,
2015 is that the
Rules do not permit the consolidation of arbitrations commenced under different sets of
institutional
arbitration rules (for example, the Chartered Institute of Arbitrators Rules). In fact, the
rules provide that
consolidation of the arbitration proceedings can only take place where all the proceedings are
commenced under its rules.
The lack of arbitral institutions with institutional rules that allow consolidation of various
arbitral
proceedings instituted under different rules negatively affects parties in multi-party
contractual
disputes, especially those involving construction. For this reason, some people have felt that
the
arbitration institutions are not fully serving their needs.
In light of the above, parties in construction disputes should address consolidation of
arbitrations in
their contracts to avoid any issues that may arise if separate arbitrations are filed. Depending
on the
parties’ preference and the given project, that clause may preclude consolidation, require the
other
parties’ consent to consolidate related arbitrations, or provide for automatic consolidation
upon the
request of either party. Lastly, consolidation should be sought as promptly as possible.
On 21 April 2023, the Supreme Court of Kenya delivered a ground-breaking judgment in
the
case of Dina Management
Limited vs County Government of Mombasa & Others...